Gas supply resumes after almost 2 days

Gas crisis file photo
Gas crisis file photo

Gas supply resumed in the capital and its adjacent areas on Sunday morning almost two days after it was partially halted due to a technical glitch at Ashulia gas station of the state-run Gas Transmission Company Ltd (GTCL), reports UNB.

"The supply was resumed around 10am on Sunday after replacing a valve of the transmission line in Ashulia," a general manager of GTCL told UNB.

The supply of gas to different areas of the capital, including Mirpur, Mohammadpur, Kalabagan, Shyamoli, Agargaon and some adjacent areas including Dhamrai, Ashulia, Aminbazar, Savar and Manikganj came to a complete or partial halt on Saturday morning as the valve started malfunctioning, according to GTCL officials.

Tens of thousands of households, factories and other establishments in the affected areas had experienced untold sufferings due to sudden stoppage of the supply.

Titas Gas is responsible for the distribution of gas in Dhaka city, Savar and Manikganj while GTCL is responsible for gas transmission across the country.