Padma bridge’s 25th span installed

Prothom Alo File Photo
Prothom Alo File Photo

The 25th span of the 6.15-kilometre long Padma bridge was installed on the 29th and the 30th pillars at Jajira point in Shariatpur district this afternoon.

“With the installation of the span, 3,750 meters of the main structure of the mega bridge has become visible,” deputy assistant engineer of the bridge project Humayun Kabir told BSS.

He also said installation of all 41 spans will be completed within next July as three spans would be set up in a month.

Besides, the construction of 38 pillars has already been finished among 42 pillars.

Earlier on 14 October 2018, prime minister Sheikh Hasina unveiled the name plaque of Padma bridge at the Mawa end.

Along with the spans installation, construction work of roadway slabs and railway slabs is also progressing simultaneously, the official added.